Developed by Blackford Renewables Ltd, Blackford Energy Park BESS will be a 500-megawatt project.
The grid connection has been accelerated by NESO (National Energy System Operator) to 2029, and this will help enable more renewable energy generation to be connected to the Grid for CP30 (Clean Power 2030).
The project has been developed in accordance with local and national guidelines to cause minimal impact to the local area and the site will play a key role in the transition to Net Zero.
Why do we need a BESS?
Renewable energy sources such as wind and solar power are becoming increasingly important, but they can be intermittent.
This means that they do not always produce electricity when it is needed. Energy storage systems like BESS can help to balance supply and demand,
ensuring that there is always enough electricity available. The UK is one of the world leaders in wind power generation and therefore a significant
investment in supporting infrastructure is required. This is especially prevalent in Scotland where there is a lot of wind generation and
transmission around the UK.
Public Consultation
We will be hosting a second public consultation event at Rothienorman Village Hall on 3 April between 4 p.m. and 7 p.m. We look forward to meeting you and hearing your feedback.
The feedback will be used to inform our full planning application. If you would like to provide feedback online, please fill out
our feedback form linked below.
The noise from the air conditioning units for the battery containers,
as well as the additional transformer needs to be considered against the baseline of pre-Rothienorman substation levels,
and additionally modelled for all six of the proposed BESS sites operating at the same time,
along with the existing noise from the substation and the Grid Stability Facility
Based on guidance from Aberdeenshire council, a noise report will be submitted with the full planning application
and shall assess the noise emitted from this project. In addition, the noise report will consider the cumulative
effects of nearby developments, including the substation, Grid Stability Facility, and directly adjacent BESS project.
The cumulative aspect is in order of consenting, so a new application will need to consider all those that go before.
It will need to be ensured that the cumulative noise levels at local dwellings fall within the NR20 criteria.
An NR20 environment is characterised by very low background noise, comparable to a quiet bedroom or library,
making it suitable for spaces requiring minimal disturbance. The criteria of an NR20 environment involves defining maximum noise levels,
in decibels, for each octave band (i.e. groups of noise organised by pitch).
A baseline assessment of this project has already been completed by specialist noise consultants,
which takes into account the nearby developments and existing background noise as part of assessing against Council requirements.
In addition, we understand that there is another BESS project nearby to local dwellings south of Blackford Energy Park.
In both cases however, the cumulative noise levels are predicted to be far below the NR20 criteria at these dwellings.
This full report will be required to demonstrate that the site is compliant with the NR20 limits imposed by the Council.
To ensure compliance, and to make sure there is no noise nuisance for local residents, the battery chillers/air-conditioners
will be fitted with attenuation silencers. As well as this, there will be acoustic barrier fencing around the equipment
which is used to absorb and deflect noise away. This report will be made public, and is reviewed by the council, the ECU,
and their own independent technical consultants.
It is not possible to extinguish a lithium-ion battery fire - what is the plan for containment,
both within the site, and cumulatively across all of the BESS sites? Particularly bearing in mind the fire at the local Overhill site,
and at Tilbury Essex site just recently. An emergency response plan is required for the site and for the area as a whole -
including evacuation of residential properties and livestock
An emergency response plan will be written for the site; the emergency services will be consulted and informed throughout,
any impacted residents will be updated accordingly. The site has been designed to minimise risk and impacts so that in the
exceptional event of one battery catching fire, it will not spread to other battery units. Fire can not spread between individual
sites as each site is significantly isolated from one another.
The composition of the batteries is still under consideration but is likely to be:
There is not a mains water connection in Blackford. As water will need to be stored,
what volume is required, and how will this water be sourced (if a borehole is used, this affects the private water supplies of local residents).
There will be large water tanks spaced around the site which could be used for fire containment if required.
They will be sized according to the NFCC guidance and store approximately one million litres in total on site.
Once filled, they will not need to be replenished unless used. The initial filling will not impact other water supplies in the area.
It is likely there will be a private water supply installed for maintenance workers.
What is the plan to prevent water used going back into the local eco-system after it has been contaminated?
If the water used to treat the fire gets into the local water table, that is not acceptable - residents all have private water supplies,
and there is a burn that runs directly into Rothienorman village.
Highlighted by recent events in the UK and comments from the first public consultation we understand this has become a primary concern for those who could be impacted.
We are working with consultants and experts to ensure that the drainage and water run-off mitigation plan for the BESS project is controlled,
robust and acceptable to the public and the planning authorities. We work closely with the authorities and the fire service both locally and
nationally to ensure we meet or exceed the current recommendations and that our development is future-proofed to ensure compliance for any
future recommendations and/or legislation.
During construction, there will be major disruption on single track roads from both the 100+ construction workers arriving and leaving each day,
along with the heavy goods vehicle deliveries for all of the concrete and the equipment. There will also be construction noise and light pollution.
During the first public consultation and the subsequent follow-up communication with the public, we have been made aware of the volume of construction
traffic and personnel that have been using the lanes around Rothienorman in recent years. We are also aware that some sites have been illuminated
throughout the night leading to significant temporary light pollution during their construction periods and understand the impact this has on the community.
Therefore, we are instigating a robust plan for the movement of construction traffic and personnel and to minimise, where possible, any light
pollution during the construction period.
When operational, the site will be unmanned and not illuminated. There will be security lighting but this will only be used if required.
There will be the occasional visits to the site during its operation for maintenance or breakdowns of equipment and for landscaping maintenance.
We appreciate that there will be some inconvenience to the general public during the construction period. Deliveries to the site will only be between
the hours of 8 a.m. - 6 p.m. Monday to Friday, 9 a.m. - 1 p.m. on Saturday and no deliveries on Sundays.
As a professional BESS developer who delivered the UK's first ever BESS project, we take our responsibilities seriously. We ensure that all our employees,
subcontractors and third parties do not make use of unauthorised private property, nor discard litter from vehicles, or use unauthorised routes to and from the
site, not observe speed limits or otherwise impact peoples quality of life beyond those that are required to construct and operate the site. We will provide
a point of contact on site during the construction period to report any infringements.
Where are the guarantees that the land will be restored at the end of the 25-years of the project - for example, how is the concrete going to be removed from the ground,
and is there a secured fund for the money required to carry out this work?
After the site has reached the end of its life, all equipment is removed from the site and repurposed, reused or recycled where possible.
All construction materials, and cables at a depth of up to 1m, are also removed and are recycled where appropriate.
The berms around the site are to be formed from the removal of the top soil during construction and this will be reinstated at the end of
the project's life. By storing the top soil in the same field that it was removed from, this reduces the amount of traffic during construction
and also reinstatement as new topsoil does not need to be reintroduced. Photographic evidence of the land is documented prior to any construction
works being carried out to ensure the land is reinstated to the state as required by the planning authorities and the Landlord.
A reinstatement bond and the agreed mechanism will be a planning condition. The planning authorities (Local planning Authority and the Energy
Consents Unit) are generally a named party to the agreement. The bond value is reviewed independently every five years by all named parties
to ensure that there is sufficient funding in place for reinstatement as required by the Planning Authorities and the planning conditions.
This is a rural, agricultural area. The creeping industrialisation of this area is changing its character, changing the landscape and
greatly impacting on the nature of the land. This impacts the people who live here, people who visit here and, most importantly,
the animals who make this area their home.
We recognise that there is an impact, but do as much as we can to mitigate it through sensitive design.
The land will be fully reinstated at the end of the project's lifecycle, as required by the Planning Authorities and the Landlord.
We are aware of the impact these projects have on the nature of the land, therefore, as a responsible developer, our landscaping plan,
tree planting, introduction of nature corridors and creating habitats will enhance the area's wildlife whilst protecting existing wildlife.
By planting trees of the local area, ensuring invasive species of plants are not introduced and not importing soil from outside of the area,
we want the project to blend into the area and not impact people's day-to-day lives once operational.
The BESS project is a requirement for the transition to a fully renewable electrical supply and will provide grid stability and frequency services
to the national grid transmission network as well as energy arbitrage (importing at times of renewable over-supply, exporting at times of under-supply).
Ongoing planning induces stress in local residents each time a new application appears. The stress and worry about impacts on our landscape,
our environment and inherent risks with BESS facilities is adversely affecting our mental health. Stress also impacts on our physical health
due to sleep deprivation, blood pressure etc.
As a responsible employer, we take the mental and physical health of our employees and those affected by our projects seriously.
We do not underestimate the cumulative effect that the ongoing construction works around Rothienorman have taken on those affected.
Our project is not due to start construction until 2028 and we will continue to modify and update our plans to ensure we minimise the
impact on the daily lives of residents during the construction and operation of the site.
We want to ensure that any discharge into watercourses is done in a way that ensures that the project does not impact private water supplies,
increase the flood risk, or contaminate burns (streams or brooks). We carry out extensive modelling and employ consultants to ensure that issues
do not arise. Our consultants' reports are independently verified and will be made public when planning is submitted to the Scottish Energy Consents Unit.
We are contacting everyone in the area with a private water supply to enable our consultants to understand any measures that need to be taken to
protect the supply of water. Please respond to the survey so we can help you protect it.
Recently, I have noticed changes in my Private Water Supply, road damage, littering, noise, light pollution etc.
This project's construction would not start until 2028, therefore anything you are currently observing is not related to this project.
However, as feedback suggests, this is a common issue with other projects in the area. We have a responsibility to our neighbours and a duty of
care to minimise disruption and be proactive in mitigating against potential issues before they arise.
We will ensure that the impact of the project to the surrounding area is reviewed and where necessary, take action against individuals employed by us,
directly or indirectly and provide the public with recourse should problems arise. We intend to provide easy means of reporting nuisance to the site
management, including named individuals, who can then follow up with contractors and delivery companies.
How can we trust your consultants and reports?
We use independent and reputable consultants who are paid by us to assess our project in the specific area they specialise in. They write a report
with recommendations which we supply to the council as part of our planning application. These consultants rely on their reputation for future
business, and their reports are always made public as part of the application process. The reports are reviewed by the council and the ECU, and
their own independent consultants who verify and comment on the analysis. This ensures the reports generated for this project are accurate and
adhere to local and national standards of practice. In this respect, the planning process is quite rigorous, and by following such procedures the
quality of planning applications, and the conditions attached to their consent, lead to improvement in the quality of projects, and ensure
mitigations are both proposed and enforced.
Site Selection
Proximity to the substation
The site is adjacent to the electricity substation which is an ideal location for electrical infrastructure which supports the grid.
Noise
A noise study has been undertaken which shows that the combination of equipment selected and site location will have negligible impact on local residents.
The assessment checked for any cumulative impact from other nearby energy developments and infrastructure.
Visual impact
The site has been designed and landscaped to provide negligible impact to those who live around or are travelling through the area.
The site will only be visible from a few view points and mostly obscured by trees and planting.
Private Water Supplies
A Private Water Supply assessment is currently being undertaken. If you have received a survey in the post, please respond so we can take appropriate action.
Fire Safety
Fire risk has been considered from the earliest stages of development and will continue to be a key focus for risk mitigation.
The site will comply with the National Fire Chiefs Council guidance and the local fire service will be consulted for their comments throughout the design, construction and operational phases.
Heritage and Archaeology
A baseline assessment has been undertaken, and further trenching works will be required to assess the entire site area.
Previous trenching works in the field have found no evidence of archaeological discovery.
Get In Touch
If you have any questions or would like to get in touch with us, please contact us using the details below: